Find help with concrete cancer repairs for Melbourne properties.

Facade concrete remediation in Melbourne

Repairing concrete cancer on Melbourne building facades: spandrels, columns and slab edges, access methods, permits for footpath scaffold and costs.

Facade remediation fixes concrete cancer on the outside face of a building: slab edges, spandrel beams, columns, sunshades and panels. Because the work is at height and often over a footpath, most of the planning goes into the survey, the access method and council permits before any concrete is cut out.

Illustrative photo for Facade concrete remediation in Melbourne

What goes wrong on concrete facades?

Exposed concrete on the outside of a building takes rain, sun and, near the bay, salt in the air. Cement Concrete & Aggregates Australia’s report on chloride resistance describes coastal structures receiving considerable chloride from the atmosphere, deposited on surfaces or washed off by rain, and explains that carbonation of the surface can free up chlorides already bound in the concrete. Corroding steel then cracks the cover and drops pieces of it.

Typical facade defects:

  • Spalled slab edges at each floor line.
  • Cracked or rust-stained spandrels below windows.
  • Column corners breaking away.
  • Rusting fixings for awnings, signs or balustrades set into the face.
  • Old patch repairs that have drummed or come loose.
  • Cracked render or paint hiding damage underneath.

Falling concrete from a facade is a public safety problem as well as a maintenance one. Barricade the footpath area under any loose section and report it to the building manager straight away.

How a facade survey is done

Before pricing a whole building, most providers or engineers survey it. The survey usually maps every defect by elevation and floor, sounds the concrete for hollow areas, measures cover over the steel at sample points, and records photos. Testing for carbonation depth and chloride content shows whether damage is likely to keep spreading; see carbonation and chloride testing. The survey becomes the basis for a schedule of quantities that every quoting provider can price the same way.

Access options compared

Access method Good for Watch for
Scaffold Full facade programs, heavy breakout, multiple trades Footpath and road permits, longer setup
Boom lift or knuckle boom Low and mid-rise blocks with ground access Ground bearing, reach, traffic control
Swing stage Tall facades with roof anchor points Anchor certification, wind limits
Rope access Spot repairs and surveys on tall buildings Limited for heavy breakout and large patches

The method affects the price as much as the concrete repair does. Ask each provider to price access as its own line.

Council permits for work over a footpath

Each council has its own rules for scaffold and hoardings on public land:

  • In the city, anything temporary that protects the public and stands on council roads or footpaths, whether scaffold, gantry or hoarding, needs a City of Melbourne temporary protective structure permit. Applicants supply a structural engineer’s certificate of compliance, a traffic management plan and a public liability insurance certificate. A structure that projects over the street alignment needs a report and consent first.
  • The City of Port Phillip requires a street occupation permit whenever any part of a road or lane is used for construction, including hoardings and scaffolding.
  • The City of Stonnington requires Local Law permits for hoardings on Council land and for occupying a footpath.

The Melbourne CBD page and the Port Melbourne page cover these in more detail.

What the repair work involves

On each defect the provider breaks out to sound concrete, cleans and primes the exposed steel, and rebuilds with repair mortar matched to the face. The Quote Yard’s Victorian concrete repair guide notes that full concrete cancer remediation on a single multi-storey balcony soffit can extend across two to three weeks, so a whole facade is planned as a staged program. Afterwards the facade is often coated so the repairs and the surrounding concrete are protected; see protective coatings and sealing.

Breaking out and grinding concrete makes crystalline silica dust. WorkSafe Victoria says concrete contains crystalline silica and that a hazard control statement must be prepared before high risk crystalline silica work begins. Older buildings may also have asbestos in sealants, packers or fibre cement panels; WorkSafe notes asbestos is still found in more than 3000 building products and keeps a directory of licensed asbestos removalists.

Heritage buildings

Many inner Melbourne facades sit in a Heritage Overlay. Under clause 43.01 of the Victoria Planning Provisions, a permit is needed for works, repairs and routine maintenance that change the appearance of a heritage place or are not done to the same details, specifications and materials, and to paint a previously unpainted surface. Check the address on VicPlan before agreeing to coat bare off-form concrete.

What it costs

The Quote Yard lists concrete cancer remediation in Victoria at $200 to $500 per sqm, with scaffolding for elevated work and engineering assessment usually extra. On a facade the access and permits can match or exceed the repair cost. The concrete cancer cost guide explains how to compare quotes built on a survey schedule.

Rules and checks

The Building and Plumbing Commission says some work always needs a registered practitioner regardless of cost, including structural work. Check the builder on the BPC register and the engineer on the Victorian professional engineers register. If loose facade concrete threatens people below, the council’s municipal building surveyor has power under the Building Act 1993 to issue an emergency order to the owner.

What a careful provider will never skip

  • A defect map tied to elevations, so repairs can be measured and paid accurately.
  • Exclusion zones and overhead protection while breakout is under way.
  • Dust controls and a silica hazard control statement where required.
  • Photos of each repair at breakout and after priming, before it is covered.

What to do next

Gather any facade survey, engineer’s report or past repair records, with photos of each elevation. Then ask for facade remediation quotes. The site sends enquiries on to independent remediation businesses, and the business you engage is the one responsible for permits, safety and workmanship.

Send a job enquiry

Frequently asked questions

Do we need a full facade survey before getting quotes?

For anything beyond a few obvious spalls, yes. A survey that maps each defect by elevation and floor gives every provider the same quantities to price, which makes quotes comparable and reduces arguments about variations later.

Can repairs be done without scaffolding?

Sometimes. Boom lifts, swing stages and rope access suit many buildings, especially for surveys and spot repairs. Heavy breakout across a whole elevation is usually easier and safer from scaffold. The right method depends on height, ground access and the amount of work.

What permits are needed for scaffold on the footpath?

Each council has its own process. The City of Melbourne requires a temporary protective structure permit, Port Phillip a street occupation permit, and Stonnington Local Law permits for hoardings and footpath occupation. Providers usually arrange these, so confirm who is responsible in the quote.

What if the building is heritage listed?

In a Heritage Overlay, a planning permit is needed for repairs that change how the place looks or do not match the original details and materials, and for painting a surface that was never painted. Check the address on VicPlan and talk to council planners early.

Can the building stay occupied during facade repairs?

Usually, with staging, exclusion zones under the work area, dust controls and notice to residents about noise. Areas directly below active breakout must be kept clear. Ask providers for a staging plan with their quote.